Boskalis busy with heavy lift ops in Dardanelles strait

Boskalis busy with heavy lift ops in Dardanelles strait

Photo source: Boskalis

The dredging and heavy lift specialist, Royal Boskalis Westminster, has recently been busy at the construction site of the longest suspension bridge in the world. The company’s floating sheerleg crane, Asian Hercules III has been lifting section pieces for the bridge spanning the Dardanelles strait. 

Boskalis informed in a brief statement that Asian Hercules III lifted and installed sixteen bridge sections for the Çanakkale 1915 Bridge in Turkey. For these lifts the Asian Hercules III had to be positioned in between the bridge cables with minimal maneuvering space.

The preparation for the project team and engineers in terms of performing motions studies, developing anchoring plans and contingency scenarios paid off and resulted in the safe and successful execution of the sixteen lifts. Previously Boskalis secured a contract to execute a part of the lifting operations, a float-over scope to install the tie-beam and deliver a part of the vessels for transport and installation of the foundation caissons.

Photo source: Boskalis

The 1915 Çanakkale Bridge

The 1915 Çanakkale Bridge, also known as the Çanakkale Strait Bridge, is a suspension bridge being constructed in the Çanakkale area in Turkey. The bridge will span the Dardanelles strait, about 10 km south of the Sea of Marmara.

With a main span of 2,023 m, the bridge will become the longest suspension bridge in the world. The total length of the bridge will be 3,563 m and together the approach viaducts the length reaches 4,608 m.

On January 26, 2017, a consortium SK Engineering & Construction, Daelim Industrial, Limak Insaat Sanayi ve Ticaret AS and Yapi Merkezi Insaat Sanayi ve Ticaret AS was appointed as contractor for the construction of the bridge. Construction activities started in 2017 and are scheduled to be completed by March 2022.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Boskalis busy with heavy lift ops in Dardanelles strait | Project Cargo Journal
Boskalis busy with heavy lift ops in Dardanelles strait

Boskalis busy with heavy lift ops in Dardanelles strait

Photo source: Boskalis

The dredging and heavy lift specialist, Royal Boskalis Westminster, has recently been busy at the construction site of the longest suspension bridge in the world. The company’s floating sheerleg crane, Asian Hercules III has been lifting section pieces for the bridge spanning the Dardanelles strait. 

Boskalis informed in a brief statement that Asian Hercules III lifted and installed sixteen bridge sections for the Çanakkale 1915 Bridge in Turkey. For these lifts the Asian Hercules III had to be positioned in between the bridge cables with minimal maneuvering space.

The preparation for the project team and engineers in terms of performing motions studies, developing anchoring plans and contingency scenarios paid off and resulted in the safe and successful execution of the sixteen lifts. Previously Boskalis secured a contract to execute a part of the lifting operations, a float-over scope to install the tie-beam and deliver a part of the vessels for transport and installation of the foundation caissons.

Photo source: Boskalis

The 1915 Çanakkale Bridge

The 1915 Çanakkale Bridge, also known as the Çanakkale Strait Bridge, is a suspension bridge being constructed in the Çanakkale area in Turkey. The bridge will span the Dardanelles strait, about 10 km south of the Sea of Marmara.

With a main span of 2,023 m, the bridge will become the longest suspension bridge in the world. The total length of the bridge will be 3,563 m and together the approach viaducts the length reaches 4,608 m.

On January 26, 2017, a consortium SK Engineering & Construction, Daelim Industrial, Limak Insaat Sanayi ve Ticaret AS and Yapi Merkezi Insaat Sanayi ve Ticaret AS was appointed as contractor for the construction of the bridge. Construction activities started in 2017 and are scheduled to be completed by March 2022.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.