Hornsea Two monopile foundations in place

Hornsea Two monopile foundations in place

Photo source: DEME

The installation of the 165 monopile foundations at Ørsted’s Hornsea Two wind farm has come to a close. DEME Offshore said it has installed the final monopile foundation at the currently largest offshore wind farm in the world. 

Bart De Poorter, General Manager DEME Offshore Renewables, stressed that the 165 foundations have been transported and installed in just one year.

“DEME’s logistics and engineering teams have put in an extraordinary performance. They had to ensure a continual flow of components which were transported from three different fabrication ports to the base port in Eemshaven in the Netherlands. The heaviest piles weighed around 1,250 tonnes and had a diameter of 9.5 metres, therefore DEME Offshore’s engineers designed specialist equipment to make the installation process as efficient as possible,” Bart De Poorter said.

Currently, DEME Offshore’s sister vessels Sea Installer and Sea Challenger are installing the 165 8 MW Siemens Gamesa turbines. With over 100 turbines now installed, the wind farm’s generation assets are well on the way to completion.

As well as the transport & installation scope for the turbines and foundations, two of DEME ’s fallpipe vessels carried out the scour protection at 89 locations.

Located approximately 89 km off the Yorkshire coast, Hornsea Two will generate up to 1.4GW of clean energy for UK households when fully operational in 2022.

Hornsea Two is the third offshore wind farm project where DEME Offshore has been responsible for the installation of more than 100 foundations.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Hornsea Two monopile foundations in place | Project Cargo Journal
Hornsea Two monopile foundations in place

Hornsea Two monopile foundations in place

Photo source: DEME

The installation of the 165 monopile foundations at Ørsted’s Hornsea Two wind farm has come to a close. DEME Offshore said it has installed the final monopile foundation at the currently largest offshore wind farm in the world. 

Bart De Poorter, General Manager DEME Offshore Renewables, stressed that the 165 foundations have been transported and installed in just one year.

“DEME’s logistics and engineering teams have put in an extraordinary performance. They had to ensure a continual flow of components which were transported from three different fabrication ports to the base port in Eemshaven in the Netherlands. The heaviest piles weighed around 1,250 tonnes and had a diameter of 9.5 metres, therefore DEME Offshore’s engineers designed specialist equipment to make the installation process as efficient as possible,” Bart De Poorter said.

Currently, DEME Offshore’s sister vessels Sea Installer and Sea Challenger are installing the 165 8 MW Siemens Gamesa turbines. With over 100 turbines now installed, the wind farm’s generation assets are well on the way to completion.

As well as the transport & installation scope for the turbines and foundations, two of DEME ’s fallpipe vessels carried out the scour protection at 89 locations.

Located approximately 89 km off the Yorkshire coast, Hornsea Two will generate up to 1.4GW of clean energy for UK households when fully operational in 2022.

Hornsea Two is the third offshore wind farm project where DEME Offshore has been responsible for the installation of more than 100 foundations.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.