Deep South lifts heavy in process plant overhaul

Deep South lifts heavy in process plant overhaul

Photo source: Deep South

Deep South crews were hired to haul, lift, and set 84 modules, including three towers, one measuring around 30 metres long, weighing around 150 tons, as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centres of gravity further complicating the lift and set. The work has been completed for an unnamed client overhauling its process plant. 

Conventional methods would have required using multiple sets of rigging with different length slings and several shackles to level the modules. The rigging then would have been disassembled and reassembled, making small adjustments in sling lengths or number of shackles, for every new lift, a complexity that added too much time to an already tight schedule.

Instead, Deep South deployed its Module Lifting System with 100-ton lifting capacity, an in-house designed, engineered, fabricated, and tested system designed to set multiple objects of different widths, lengths, and centres of gravity with the same rigging.

The Module Lifting System, with its specialised spreader bars and built-in hydraulic cylinders for easy adjustments, eliminated the need for more conventional rigging systems. It incorporates two 75-ton hydraulic lift cylinders to levels loads in the transverse direction with 4’-0” adjustments and multi-holed lower modular bars equipped with two 55-ton hydraulic lift cylinders to level loads in the longitudinal direction with 6’-0” adjustment. With this system in place, operators connected the hydraulic lines to a power pack unit on the ground make the length adjustments to the hydraulic cylinders then began the lifts.

In the first phase, over the course of one month, Deep South transported and set 35 modules using 18-axle-line Goldhofer trailers, 18-axle-line Scheuerle SPMTs, and a 440-ton Terex-Demag CC-2400-1 crawler crane. The second phase relied on a 660-ton Liebherr LR-1600/2 crawler crane to move and set 49 modules over the course of two months. Each phase relied upon Deep South’s Module Lifting System as the rigging.

Author: Adnan Bajic

1 comment op “Deep South lifts heavy in process plant overhaul”

Madras Guide|14.02.22|11:55

Thanks for Sharing article about Hydraulic Powerpack. Here, Hindustan – One of the Leading Hydraulic Power pack Manufacturers in Chennai, They’re engaged in offering a comprehensive range of Hydraulic Power Pack to the Customers. You can mileage these products in different specifications from Them. Call 9840921885 to get Latest Offer Prices.

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Deep South lifts heavy in process plant overhaul | Project Cargo Journal
Deep South lifts heavy in process plant overhaul

Deep South lifts heavy in process plant overhaul

Photo source: Deep South

Deep South crews were hired to haul, lift, and set 84 modules, including three towers, one measuring around 30 metres long, weighing around 150 tons, as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centres of gravity further complicating the lift and set. The work has been completed for an unnamed client overhauling its process plant. 

Conventional methods would have required using multiple sets of rigging with different length slings and several shackles to level the modules. The rigging then would have been disassembled and reassembled, making small adjustments in sling lengths or number of shackles, for every new lift, a complexity that added too much time to an already tight schedule.

Instead, Deep South deployed its Module Lifting System with 100-ton lifting capacity, an in-house designed, engineered, fabricated, and tested system designed to set multiple objects of different widths, lengths, and centres of gravity with the same rigging.

The Module Lifting System, with its specialised spreader bars and built-in hydraulic cylinders for easy adjustments, eliminated the need for more conventional rigging systems. It incorporates two 75-ton hydraulic lift cylinders to levels loads in the transverse direction with 4’-0” adjustments and multi-holed lower modular bars equipped with two 55-ton hydraulic lift cylinders to level loads in the longitudinal direction with 6’-0” adjustment. With this system in place, operators connected the hydraulic lines to a power pack unit on the ground make the length adjustments to the hydraulic cylinders then began the lifts.

In the first phase, over the course of one month, Deep South transported and set 35 modules using 18-axle-line Goldhofer trailers, 18-axle-line Scheuerle SPMTs, and a 440-ton Terex-Demag CC-2400-1 crawler crane. The second phase relied on a 660-ton Liebherr LR-1600/2 crawler crane to move and set 49 modules over the course of two months. Each phase relied upon Deep South’s Module Lifting System as the rigging.

Author: Adnan Bajic

1 comment op “Deep South lifts heavy in process plant overhaul”

Madras Guide|14.02.22|11:55

Thanks for Sharing article about Hydraulic Powerpack. Here, Hindustan – One of the Leading Hydraulic Power pack Manufacturers in Chennai, They’re engaged in offering a comprehensive range of Hydraulic Power Pack to the Customers. You can mileage these products in different specifications from Them. Call 9840921885 to get Latest Offer Prices.

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.