DolWin kappa platform sails out of Cadiz

DolWin kappa platform sails out of Cadiz

Photo source: TenneT

TenneT will be able to provide more power via the direct current connection DolWin6, now that the 900 MW offshore platform DolWin kappa sailed out from the Dragados Offshore shipyard in Cádiz, Spain. With this, Europe’s major offshore transmission system operator, has reached a new milestone in its quest to bringing more green wind power from the German North Sea to land.

After only three years of construction, the platform is now on board the transport barge Iron Lady and on its way to the Dutch port of Rotterdam. There, it will be reloaded onto the world’s largest service vessel, the Pioneering Spirit, and then shipped to the installation site. The grid connection system is scheduled to be commissioned in 2023 and provide renewable energy to over 1 million households.

“TenneT is taking its mission seriously and advancing the grid expansion in the North Sea step by step. With the successful sail-out of the offshore platform DolWin kappa, we have taken the next important leap. DolWin6 is already the 13th offshore grid connection in our German portfolio and will bolster Europe’s urgently needed energy independence beginning in 2023,” said TenneT COO Tim Meyerjürgens when the platform set sail.

“We also have our partners to thank for the fact that we are reaching this milestone on schedule. Working closely with our contractors Siemens Energy and Dragados Offshore, my colleagues took only three years to build the platform despite the enormous challenges posed by the pandemic. This is an outstanding achievement – and proof that we have strong, reliable partners,” Meyerjürgens added.

DolWin kappa platform sails out of Cadiz
Photo source: TenneT

DolWin kappa platform

The platform consists of a foundation structure (jacket) and a superstructure (topside). The two have a combined height of about 82 metres, so the platform will rise about 53 metres above the surface of the North Sea. In addition, there will be a bridge that will connect DolWin kappa with DolWin beta (grid connection system DolWin2), which was already commissioned in 2016, in order to efficiently use the already existing infrastructure of the parent platform. What’s more, the overall optimised design of the platform has significantly reduced the size of DolWin kappa.

“The well-thought-out construction of the offshore platform conserves important resources while minimising impacts on the environment. This clearly illustrates that protecting the environment and nature is our top priority when planning and implementing our grid connections,” Tim Meyerjürgens said.

Once it arrives in Rotterdam, the platform will be reloaded onto the world’s largest service vessel. The 382-metre long Pioneering Spirit will carry all platform components (jacket, topside, piles and bridge) to their final destination in the German North Sea. Once there, DolWin kappa will be installed directly from the work boat.

After the platform is commissioned in 2023, it will convert the alternating current generated by offshore wind farms into direct current, which will then be transmitted to Hilgenriedersiel on the mainland via an approximately 45 kilometre-long subsea cable. From the landfall in Hilgenriedersiel, the electricity will be transmitted to Emden by a land cable, which will also be 45 kilometres long. Here on land, TenneT has built the Emden/Ost converter station and transformer station to convert the direct current back into alternating current and then feed it into the high-voltage grid at the correct voltage level.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

DolWin kappa platform sails out of Cadiz | Project Cargo Journal
DolWin kappa platform sails out of Cadiz

DolWin kappa platform sails out of Cadiz

Photo source: TenneT

TenneT will be able to provide more power via the direct current connection DolWin6, now that the 900 MW offshore platform DolWin kappa sailed out from the Dragados Offshore shipyard in Cádiz, Spain. With this, Europe’s major offshore transmission system operator, has reached a new milestone in its quest to bringing more green wind power from the German North Sea to land.

After only three years of construction, the platform is now on board the transport barge Iron Lady and on its way to the Dutch port of Rotterdam. There, it will be reloaded onto the world’s largest service vessel, the Pioneering Spirit, and then shipped to the installation site. The grid connection system is scheduled to be commissioned in 2023 and provide renewable energy to over 1 million households.

“TenneT is taking its mission seriously and advancing the grid expansion in the North Sea step by step. With the successful sail-out of the offshore platform DolWin kappa, we have taken the next important leap. DolWin6 is already the 13th offshore grid connection in our German portfolio and will bolster Europe’s urgently needed energy independence beginning in 2023,” said TenneT COO Tim Meyerjürgens when the platform set sail.

“We also have our partners to thank for the fact that we are reaching this milestone on schedule. Working closely with our contractors Siemens Energy and Dragados Offshore, my colleagues took only three years to build the platform despite the enormous challenges posed by the pandemic. This is an outstanding achievement – and proof that we have strong, reliable partners,” Meyerjürgens added.

DolWin kappa platform sails out of Cadiz
Photo source: TenneT

DolWin kappa platform

The platform consists of a foundation structure (jacket) and a superstructure (topside). The two have a combined height of about 82 metres, so the platform will rise about 53 metres above the surface of the North Sea. In addition, there will be a bridge that will connect DolWin kappa with DolWin beta (grid connection system DolWin2), which was already commissioned in 2016, in order to efficiently use the already existing infrastructure of the parent platform. What’s more, the overall optimised design of the platform has significantly reduced the size of DolWin kappa.

“The well-thought-out construction of the offshore platform conserves important resources while minimising impacts on the environment. This clearly illustrates that protecting the environment and nature is our top priority when planning and implementing our grid connections,” Tim Meyerjürgens said.

Once it arrives in Rotterdam, the platform will be reloaded onto the world’s largest service vessel. The 382-metre long Pioneering Spirit will carry all platform components (jacket, topside, piles and bridge) to their final destination in the German North Sea. Once there, DolWin kappa will be installed directly from the work boat.

After the platform is commissioned in 2023, it will convert the alternating current generated by offshore wind farms into direct current, which will then be transmitted to Hilgenriedersiel on the mainland via an approximately 45 kilometre-long subsea cable. From the landfall in Hilgenriedersiel, the electricity will be transmitted to Emden by a land cable, which will also be 45 kilometres long. Here on land, TenneT has built the Emden/Ost converter station and transformer station to convert the direct current back into alternating current and then feed it into the high-voltage grid at the correct voltage level.

Author: Adnan Bajic