Mammoet heavy lift works continue at Barmer complex in India

Mammoet heavy lift works continue at Barmer complex in India

Photo source: Mammoet

Mammoet has continued its heavy lift work at the Barmer oil refinery and petrochemical complex in Rajasthan, India, for L&T Hydrocarbon Engineering. The company will be utilising its PTC ring cranes to lift and install a range of modules at HPCL Rajasthan Refinery.

Specifically, two ring cranes will be employed: the PT50 ring crane will lift and install reactors, regenerators and fractionators, while the PTC35-DS will lift and install a 127m long C3 rectifier (in three parts) and a quench water tower, Mammoet informs.

The ring cranes will allow L&T to install the reactors and regenerators in just two sections, instead of four sections if a conventional crawler crane is used. The PTC35-DS will prevent unnecessary sectioning and lifting of the equipment into five parts. Therefore, there will be a reduction in total lead time and overall cost savings for the customer. The lifting works are expected to start taking place on site in the middle of 2022.

In addition, the ring crane’s base has a small area of only 27.5 square meters, as compared to a conventional crawler crane’s base which is much larger at 60 square meters and requires multi-location re-positioning. This provides the customer with other benefits such as on-site space savings and minimal on-site disruption, allowing other vendors to execute work simultaneously with Mammoet – saving overall construction lead time.

“Mammoet started working closely with L&T Hydrocarbon Engineering from an early bid phase, which enabled creation of both technically sound and cost-effective solutions. Some lifts required for reactors, regenerators and C3 rectifiers required us to engineer sequenced lifting and provide critical changes in equipment design.

An operation of multiple lifts at a single crane position with one boom configuration is a cost-effective solution for the customer,” states Rahul Rathod, head of Commercial and Operations for Mammoet India.

The Barmer refinery and petrochemical complex is developed for the production of cleaner fuels and is the first of its kind in Rajasthan. Once completed, it will have a total processing capacity of nine million metric tonnes per annum. Expected to be in production by end of 2023, the development is also expected to create approximately 1,500 direct jobs and contribute to Rajasthan’s economic development.

Tags:

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Mammoet heavy lift works continue at Barmer complex in India | Project Cargo Journal
Mammoet heavy lift works continue at Barmer complex in India

Mammoet heavy lift works continue at Barmer complex in India

Photo source: Mammoet

Mammoet has continued its heavy lift work at the Barmer oil refinery and petrochemical complex in Rajasthan, India, for L&T Hydrocarbon Engineering. The company will be utilising its PTC ring cranes to lift and install a range of modules at HPCL Rajasthan Refinery.

Specifically, two ring cranes will be employed: the PT50 ring crane will lift and install reactors, regenerators and fractionators, while the PTC35-DS will lift and install a 127m long C3 rectifier (in three parts) and a quench water tower, Mammoet informs.

The ring cranes will allow L&T to install the reactors and regenerators in just two sections, instead of four sections if a conventional crawler crane is used. The PTC35-DS will prevent unnecessary sectioning and lifting of the equipment into five parts. Therefore, there will be a reduction in total lead time and overall cost savings for the customer. The lifting works are expected to start taking place on site in the middle of 2022.

In addition, the ring crane’s base has a small area of only 27.5 square meters, as compared to a conventional crawler crane’s base which is much larger at 60 square meters and requires multi-location re-positioning. This provides the customer with other benefits such as on-site space savings and minimal on-site disruption, allowing other vendors to execute work simultaneously with Mammoet – saving overall construction lead time.

“Mammoet started working closely with L&T Hydrocarbon Engineering from an early bid phase, which enabled creation of both technically sound and cost-effective solutions. Some lifts required for reactors, regenerators and C3 rectifiers required us to engineer sequenced lifting and provide critical changes in equipment design.

An operation of multiple lifts at a single crane position with one boom configuration is a cost-effective solution for the customer,” states Rahul Rathod, head of Commercial and Operations for Mammoet India.

The Barmer refinery and petrochemical complex is developed for the production of cleaner fuels and is the first of its kind in Rajasthan. Once completed, it will have a total processing capacity of nine million metric tonnes per annum. Expected to be in production by end of 2023, the development is also expected to create approximately 1,500 direct jobs and contribute to Rajasthan’s economic development.

Tags:

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.