Collett completes super transformer delivery to Scotland

Collett completes super transformer delivery to Scotland

Collett completes super transformer delivery to ScotlandCollett

UK’s abnormal loads specialist, Collett, have completed the delivery of the second and final 215 Te Super Grid transformer to the Kintore Substation in Scotland. 

Departing from the GE Facility in Stafford, the transformer was transported to Ellesmere Port utilising Collett’s 250 Te capacity Goldhofer girder bridge trailer. Loaded onto a coaster vessel, the cargo was shipped to the Port of Aberdeen. Following on, the transformer was discharged directly back onto the girder bridge by a 600 Te strut crane.

Collett completes super transformer delivery to Scotland

Concluding the final leg of the journey to the substation site, the 215Te transformer was offloaded and manoeuvred into its final position utilising our hydraulic jacking and skidding system.

Completing the Kintore substation extension project, both transformers were safely loaded, transported, shipped and positioned.

Tags:

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Collett completes super transformer delivery to Scotland | Project Cargo Journal
Collett completes super transformer delivery to Scotland

Collett completes super transformer delivery to Scotland

Collett completes super transformer delivery to Scotland Collett

UK’s abnormal loads specialist, Collett, have completed the delivery of the second and final 215 Te Super Grid transformer to the Kintore Substation in Scotland. 

Departing from the GE Facility in Stafford, the transformer was transported to Ellesmere Port utilising Collett’s 250 Te capacity Goldhofer girder bridge trailer. Loaded onto a coaster vessel, the cargo was shipped to the Port of Aberdeen. Following on, the transformer was discharged directly back onto the girder bridge by a 600 Te strut crane.

Collett completes super transformer delivery to Scotland

Concluding the final leg of the journey to the substation site, the 215Te transformer was offloaded and manoeuvred into its final position utilising our hydraulic jacking and skidding system.

Completing the Kintore substation extension project, both transformers were safely loaded, transported, shipped and positioned.