Moray West transformers reach Banffshire onshore converter station

Moray West transformers reach Banffshire onshore converter station

Photo: Allelys

Allelys recently transported two 239-tonne transformers, each measuring 12.3 meters, from Buckie Harbour, Banffshire to Moray West Onshore Converter Station.

Prior to the operation, extensive planning and engineering works were completed to overcome the harbour’s restrictive layout and limited space. Allelys also completed detailed route surveys along the route, with swept path analysis on the most restrictive areas also identifying necessary street furniture removal requirements, which would ensure the load was delivered safely and securely to the Moray West site.

The transformers were offloaded from the vessel using an LG1750 lattice boom crane and loaded directly onto SPMTs. The first unit was then transshipped onto a 24-axle girder frame trailer and laid into load hangers to allow for a more suitable offload procedure due to the long load length.

Read also: First Moray West TPs heading to Port of Nigg

Under police escort and with road closures in place, the first transformer was transported to the site. After the unit was stooled off, the girder frame was then dismantled and able to return to collect the second transformer. Simultaneously, the first transformer was jacked down and skidded 18 metres onto the designated plinth at the Moray West Onshore converter station.

The girder frame was rebuilt at the port and the second transformer was loaded, transported and installed using the same process and route as the first. Transporting the two units on consecutive weekends enabled Allelys to maintain an efficient timing schedule.

“This project has been a great example of Allelys finding an efficient and effective solution to support the power sector. The tight restrictions around the harbour are a challenge for loads such as these. However, our knowledge and experience of route planning and management ensured that we engineered a suitable solution”. Commented Jordan Heath, Project Manager at Allelys.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Moray West transformers reach Banffshire onshore converter station | Project Cargo Journal
Moray West transformers reach Banffshire onshore converter station

Moray West transformers reach Banffshire onshore converter station

Photo: Allelys

Allelys recently transported two 239-tonne transformers, each measuring 12.3 meters, from Buckie Harbour, Banffshire to Moray West Onshore Converter Station.

Prior to the operation, extensive planning and engineering works were completed to overcome the harbour’s restrictive layout and limited space. Allelys also completed detailed route surveys along the route, with swept path analysis on the most restrictive areas also identifying necessary street furniture removal requirements, which would ensure the load was delivered safely and securely to the Moray West site.

The transformers were offloaded from the vessel using an LG1750 lattice boom crane and loaded directly onto SPMTs. The first unit was then transshipped onto a 24-axle girder frame trailer and laid into load hangers to allow for a more suitable offload procedure due to the long load length.

Read also: First Moray West TPs heading to Port of Nigg

Under police escort and with road closures in place, the first transformer was transported to the site. After the unit was stooled off, the girder frame was then dismantled and able to return to collect the second transformer. Simultaneously, the first transformer was jacked down and skidded 18 metres onto the designated plinth at the Moray West Onshore converter station.

The girder frame was rebuilt at the port and the second transformer was loaded, transported and installed using the same process and route as the first. Transporting the two units on consecutive weekends enabled Allelys to maintain an efficient timing schedule.

“This project has been a great example of Allelys finding an efficient and effective solution to support the power sector. The tight restrictions around the harbour are a challenge for loads such as these. However, our knowledge and experience of route planning and management ensured that we engineered a suitable solution”. Commented Jordan Heath, Project Manager at Allelys.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.