Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project
Video

Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project

Photo source: Bolloré Logistics

Bolloré Logistics Tanzania was deployed at the Songo Songo gas development and power generation project. From June to November 2021, the company moved 5,000 freight tons of pieces and equipment for the project becoming the first company to send a large land craft on the Songo Songo island, Tanzania. 

A total of seven barge vessels were required to deliver the equipment to the island at different intervals. Several specialised pieces of equipment were used including a 130-ton and a 60-ton crane, an excavator, a modular hydraulic trailer and two semitrailers for shunting. Other difficulties involved the lack of infrastructure. To this end, a jetty had to be rebuilt and converted into a landing area capable of accommodating the vessel and cargo arriving onto the island while backfilling works were undertaken to ease the flow of vehicles being used for shunting on and off the vessel.

A team of experts was mobilised and flown to the island deploying specific logistics solutions to face the main challenges. The shifting tides notably affected the angle of the ramp used to offload the cargo, thus binding the experts to keep close watch on the inclination of the ramp.

“The main challenges were the coordination of the Customs requirements and the client’s demands, along with a lack of the equipment, including barges and ships. But with our expertise in logistics and industrial projects, we were able to deliver the required solutions with great success. All cargo was lashed and safely secured according to global QHSE standards,” said Elson Shan, cluster commercial director.

Bolloré Logistics Tanzania was contracted in 2021 to handle all logistical requirements for the project to set up a gas compression plant on Songo Songo island, located in the South of Tanzania. It was awarded to Bolloré Logistics’ teams by one of the largest suppliers in China of petroleum and petrochemical products, equipment, and technology to the global market.

Read also: Bolloré helps Côte d’Ivoire reach energy production targets

Author: Adnan Bajic

1 comment op “Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project”

Sid Survey|03.03.22|10:00

Dear Booloré Team,

I am marine cargo expert & loss adjuster and I am looking for any opportunity of survey in Africa, if you need us don’t hesistate to contact us at sidsurvey67@gmail.com / +213550684943.

B. Rgds

Sid

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project | Project Cargo Journal
Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project
Video

Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project

Photo source: Bolloré Logistics

Bolloré Logistics Tanzania was deployed at the Songo Songo gas development and power generation project. From June to November 2021, the company moved 5,000 freight tons of pieces and equipment for the project becoming the first company to send a large land craft on the Songo Songo island, Tanzania. 

A total of seven barge vessels were required to deliver the equipment to the island at different intervals. Several specialised pieces of equipment were used including a 130-ton and a 60-ton crane, an excavator, a modular hydraulic trailer and two semitrailers for shunting. Other difficulties involved the lack of infrastructure. To this end, a jetty had to be rebuilt and converted into a landing area capable of accommodating the vessel and cargo arriving onto the island while backfilling works were undertaken to ease the flow of vehicles being used for shunting on and off the vessel.

A team of experts was mobilised and flown to the island deploying specific logistics solutions to face the main challenges. The shifting tides notably affected the angle of the ramp used to offload the cargo, thus binding the experts to keep close watch on the inclination of the ramp.

“The main challenges were the coordination of the Customs requirements and the client’s demands, along with a lack of the equipment, including barges and ships. But with our expertise in logistics and industrial projects, we were able to deliver the required solutions with great success. All cargo was lashed and safely secured according to global QHSE standards,” said Elson Shan, cluster commercial director.

Bolloré Logistics Tanzania was contracted in 2021 to handle all logistical requirements for the project to set up a gas compression plant on Songo Songo island, located in the South of Tanzania. It was awarded to Bolloré Logistics’ teams by one of the largest suppliers in China of petroleum and petrochemical products, equipment, and technology to the global market.

Read also: Bolloré helps Côte d’Ivoire reach energy production targets

Author: Adnan Bajic

1 comment op “Bolloré Logistics Tanzania transports 5,000 frt for Songo Songo project”

Sid Survey|03.03.22|10:00

Dear Booloré Team,

I am marine cargo expert & loss adjuster and I am looking for any opportunity of survey in Africa, if you need us don’t hesistate to contact us at sidsurvey67@gmail.com / +213550684943.

B. Rgds

Sid

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.