Mammoet assists in 200+ ton stator replacement in Canada

Mammoet assists in 200+ ton stator replacement in Canada

Photo source: Mammoet

Mammoet recently assisted its customer, Capital Power with a two-stage emergency stator replacement at the Genesee Generating Station, located southwest of Edmonton, Alberta, Canada. The project included removal of the 209-ton existing stator building and transport of the replacement stator weighing 226 tons. 

As time is of the essence to get the Genesee 2 facility back up and running, Mammoet’s engineering team utilised its experience in moving power plant components to develop a solution for the customer, quickly developing lift plans, transport and jacking drawings.

Removing the existing stator

The first challenge faced by the project team was to remove the 209-ton existing stator from the building. To ensure the facility’s overhead cranes could safely handle a lift of this nature, Mammoet utilised steel weights to perform a load test, confirming all parameters and ensuring the functionality of the cranes.

After the load test and checks were complete, the existing stator was removed and transported to a maintenance shop for future repairs.

Moving the Genesee 2 replacement stator

As the removal of the existing stator was underway, Mammoet was already planning the next phase of the job, transporting a replacement stator weighing 226 tons to Genesee from the Sundance Generating Station.

Through Mammoet’s long-standing relationships with Alberta Transportation, Geometrix and various utility providers, the necessary approval process was expedited and a safe means of transport for Capital Power’s replacement stator was developed.

Also read: Mammoet lends a hand with Pioneering Spirit’s JLS system installation

Alberta Transportation’s bridge approval requirements meant that the replacement stator had to be transported on a route measuring 135 km using a 4-file arrangement comprising 288 tires on a single trailer, to prevent excess pressure on the road surface. To leave the Sundance site, the stator was transported via self-propelled modular transporter (SPMT) to an area where it could be transloaded to the road transport arrangement.

Once the stator arrived at Genesee, another transload to SPMT was required to allow the stator to make its way to its new home. Through a week of long hours and multiple loading and unloading the replacement stator was picked up, delivered, and installed in the Genesee plant.

Also read: Mammoet lifts heavy in Vietnam with custom-made solution

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Mammoet assists in 200+ ton stator replacement in Canada | Project Cargo Journal
Mammoet assists in 200+ ton stator replacement in Canada

Mammoet assists in 200+ ton stator replacement in Canada

Photo source: Mammoet

Mammoet recently assisted its customer, Capital Power with a two-stage emergency stator replacement at the Genesee Generating Station, located southwest of Edmonton, Alberta, Canada. The project included removal of the 209-ton existing stator building and transport of the replacement stator weighing 226 tons. 

As time is of the essence to get the Genesee 2 facility back up and running, Mammoet’s engineering team utilised its experience in moving power plant components to develop a solution for the customer, quickly developing lift plans, transport and jacking drawings.

Removing the existing stator

The first challenge faced by the project team was to remove the 209-ton existing stator from the building. To ensure the facility’s overhead cranes could safely handle a lift of this nature, Mammoet utilised steel weights to perform a load test, confirming all parameters and ensuring the functionality of the cranes.

After the load test and checks were complete, the existing stator was removed and transported to a maintenance shop for future repairs.

Moving the Genesee 2 replacement stator

As the removal of the existing stator was underway, Mammoet was already planning the next phase of the job, transporting a replacement stator weighing 226 tons to Genesee from the Sundance Generating Station.

Through Mammoet’s long-standing relationships with Alberta Transportation, Geometrix and various utility providers, the necessary approval process was expedited and a safe means of transport for Capital Power’s replacement stator was developed.

Also read: Mammoet lends a hand with Pioneering Spirit’s JLS system installation

Alberta Transportation’s bridge approval requirements meant that the replacement stator had to be transported on a route measuring 135 km using a 4-file arrangement comprising 288 tires on a single trailer, to prevent excess pressure on the road surface. To leave the Sundance site, the stator was transported via self-propelled modular transporter (SPMT) to an area where it could be transloaded to the road transport arrangement.

Once the stator arrived at Genesee, another transload to SPMT was required to allow the stator to make its way to its new home. Through a week of long hours and multiple loading and unloading the replacement stator was picked up, delivered, and installed in the Genesee plant.

Also read: Mammoet lifts heavy in Vietnam with custom-made solution

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.