Offshore wind

SAL Heavy Lift delivers new crane boom for Pacific Osprey

Foto: Swire Blue Ocean

SAL Heavy Lift has delivered a new crane boom for Swire Blue Ocean’s installation vessel Pacific Osprey. The new boom will increase the vessels maximum lift height from 97 to 132 metres, enabling it to handle the new generation of wind turbine generators. 

SAL’s heavy-lift vessel Wiebke arrived with the boom in the port of Esbjerg this weekend. Teams are onsite to offload the cargo once the weather conditions become favourable. As soon as the new crane boom is on the quayside, preparations for the installation onboard Pacific Osprey will start.

The Pacific Osprey is a 2012-built, self-elevating Windfarm Installation Vessel, originally fitted with a 1,200-tonne main crane which could lift the crane hook 97 metres above the deck at a radius of 31 metres. However, with the announcement of GE’s 12 MW Haliade-X wind turbine generator, that height is not sufficient anymore to install the future generation of wind farms. For that reason, the company decided to upgrade the vessels lift capabilities by replacing the current crane boom.

With its upgraded boom, the Pacific Osprey will be able to lift loads of 1,200 tonnes up to 132 meters above the deck at a radius of 31 metres. At a radius of 50 metres, it will be capable of lifting components weighing up 700 tonnes to a height of 128 metres above the deck.

Under normal operations, that means the vessel will be able to handle 3 12 MW GE Haliade-X wind turbine generators, 4 Siemens Gamesa 10 MW WTG’s or 5 MHI Vestas 10 MW WTG’s per loadout.

“This is an important milestone for Swire Blue Ocean. The transportation of the crane boom to Denmark rewards months of hard work spent developing a new crane boom design with capacity for future wind turbines,” says Kim Tribler, Head of Marine Operations, at Swire Blue Ocean (SBO). The Pacific Osprey is expected to return to service in May this year.

Hollandse Kust Zuid wind farm

Swire Blue Ocean has already secured a contract for its upgraded installation vessels. Vattenfall awarded SBOthe transport and installation contract for the Dutch offshore wind farm Hollandse Kust Zuid. This offshore wind farm will boast 140 11MW wind turbine generators of Siemens Gamesa which will be installed by the Pacific Osprey.

Vattenfall had selected Swire Blue Ocean prior to its tender bid to build the wind farm and both tenders, Hollandse Kust Zuid 1 & 2 and Hollandse Kust Zuid 3 & 4, were won with a zero-subsidy bid. Once fully operational, Hollandse Kust Zuid will generate enough power to supply up to three million households with green electricity.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

SAL Heavy Lift delivers new crane boom for Pacific Osprey | Project Cargo Journal
Offshore wind

SAL Heavy Lift delivers new crane boom for Pacific Osprey

Foto: Swire Blue Ocean

SAL Heavy Lift has delivered a new crane boom for Swire Blue Ocean’s installation vessel Pacific Osprey. The new boom will increase the vessels maximum lift height from 97 to 132 metres, enabling it to handle the new generation of wind turbine generators. 

SAL’s heavy-lift vessel Wiebke arrived with the boom in the port of Esbjerg this weekend. Teams are onsite to offload the cargo once the weather conditions become favourable. As soon as the new crane boom is on the quayside, preparations for the installation onboard Pacific Osprey will start.

The Pacific Osprey is a 2012-built, self-elevating Windfarm Installation Vessel, originally fitted with a 1,200-tonne main crane which could lift the crane hook 97 metres above the deck at a radius of 31 metres. However, with the announcement of GE’s 12 MW Haliade-X wind turbine generator, that height is not sufficient anymore to install the future generation of wind farms. For that reason, the company decided to upgrade the vessels lift capabilities by replacing the current crane boom.

With its upgraded boom, the Pacific Osprey will be able to lift loads of 1,200 tonnes up to 132 meters above the deck at a radius of 31 metres. At a radius of 50 metres, it will be capable of lifting components weighing up 700 tonnes to a height of 128 metres above the deck.

Under normal operations, that means the vessel will be able to handle 3 12 MW GE Haliade-X wind turbine generators, 4 Siemens Gamesa 10 MW WTG’s or 5 MHI Vestas 10 MW WTG’s per loadout.

“This is an important milestone for Swire Blue Ocean. The transportation of the crane boom to Denmark rewards months of hard work spent developing a new crane boom design with capacity for future wind turbines,” says Kim Tribler, Head of Marine Operations, at Swire Blue Ocean (SBO). The Pacific Osprey is expected to return to service in May this year.

Hollandse Kust Zuid wind farm

Swire Blue Ocean has already secured a contract for its upgraded installation vessels. Vattenfall awarded SBOthe transport and installation contract for the Dutch offshore wind farm Hollandse Kust Zuid. This offshore wind farm will boast 140 11MW wind turbine generators of Siemens Gamesa which will be installed by the Pacific Osprey.

Vattenfall had selected Swire Blue Ocean prior to its tender bid to build the wind farm and both tenders, Hollandse Kust Zuid 1 & 2 and Hollandse Kust Zuid 3 & 4, were won with a zero-subsidy bid. Once fully operational, Hollandse Kust Zuid will generate enough power to supply up to three million households with green electricity.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.