Decommissioning

Pioneering Spirit to remove two platforms in the Irish Sea

PRESS RELEASE – Allseas’ Pioneering Spirit will travel to the Irish Sea this year to remove two normally unmanned installations in the East Irish Sea. The 11,000-tonne platforms owned by Spirit Energy are used to produce gas in Morecambe Bay.

The infrastructure used to produce gas as part of Spirit Energy’s complex of eight installations in Morecambe Bay. As the field has matured, the reserves the platforms previously tapped into have been produced by the larger, manned Central Morecambe platform nearby.

The twelve wells which were connected to the DP3 and DP4 platforms have already been plugged and abandoned – using a slant rig to accommodate the angle at which the wells were drilled in the 1980s to access the gas reservoir below the seabed. Final preparations for the DP3 and DP4 installations to be lifted are underway and the platforms will soon be taken back to shore.

2 years of plannnig

Allseas’ 382-metre Pioneering Spirit will remove both platforms. “After two years of preparing the DP3 and DP4 installations for removal, we’re now looking forward to one of the most significant milestones in the project with the removal of both platforms”, says Donald Martin, project manager at Spirit Energy. “Seeing the Pioneering Spirit in the East Irish Sea will be an impressive sight – its capacity and single-lift methodology made it a good fit to safely execute this project.”

The DP3 and DP4 installations first produced gas in 1985 when the South Morecambe field came online. The area continues to produce enough gas to heat one million UK homes every day thanks to production from the Central Morecambe, North Morecambe, DP6 and DP8 platforms.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Pioneering Spirit to remove two platforms in the Irish Sea | Project Cargo Journal
Decommissioning

Pioneering Spirit to remove two platforms in the Irish Sea

PRESS RELEASE – Allseas’ Pioneering Spirit will travel to the Irish Sea this year to remove two normally unmanned installations in the East Irish Sea. The 11,000-tonne platforms owned by Spirit Energy are used to produce gas in Morecambe Bay.

The infrastructure used to produce gas as part of Spirit Energy’s complex of eight installations in Morecambe Bay. As the field has matured, the reserves the platforms previously tapped into have been produced by the larger, manned Central Morecambe platform nearby.

The twelve wells which were connected to the DP3 and DP4 platforms have already been plugged and abandoned – using a slant rig to accommodate the angle at which the wells were drilled in the 1980s to access the gas reservoir below the seabed. Final preparations for the DP3 and DP4 installations to be lifted are underway and the platforms will soon be taken back to shore.

2 years of plannnig

Allseas’ 382-metre Pioneering Spirit will remove both platforms. “After two years of preparing the DP3 and DP4 installations for removal, we’re now looking forward to one of the most significant milestones in the project with the removal of both platforms”, says Donald Martin, project manager at Spirit Energy. “Seeing the Pioneering Spirit in the East Irish Sea will be an impressive sight – its capacity and single-lift methodology made it a good fit to safely execute this project.”

The DP3 and DP4 installations first produced gas in 1985 when the South Morecambe field came online. The area continues to produce enough gas to heat one million UK homes every day thanks to production from the Central Morecambe, North Morecambe, DP6 and DP8 platforms.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.