Heerema scores He Dreiht work

Heerema scores He Dreiht work

Photo source: Heerema

Heerema Marine Contractors has been contracted by EnBW to transport and install monopiles and transition pieces at the He Dreiht offshore wind farm. 

The work includes the transport and installation of 64 monopiles and transition pieces. During operations, Heerema will use the IHC IQIP double-walled noise mitigation system NMS-10,000 amongst other systems to reduce noise pollution.

Heerema CEO, Koos-Jan van Brouwershaven said, “We are delighted to be EnBW’s chosen contractor, and we must credit the Heerema team and our client for their excellent collaboration in finding the most suited solutions for the He Dreiht project.”

He Dreiht Wind Farm

The He Dreiht wind farm is located in the German North Sea, 90 km northwest of Borkum and about 110 km west of Heligoland. With a capacity of 900 MW, He Dreiht is one of the largest planned offshore wind power projects in Europe and is scheduled to go into operation in 2025.

Heerema’s offshore wind director, Jeroen van Oosten said, “We are committed to increasing our market share in large monopile installations for offshore wind, and are proud to be chosen to enable EnBW to deliver 900 MW of renewable energy.”

EnBW He Dreiht project director, Jörn Däinghaus added, “Heerema is a contractor with a high level of experience and excellent technological know-how. We look forward to working with Heerema to develop and install our first subsidy-free offshore windpark.”

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Heerema scores He Dreiht work | Project Cargo Journal
Heerema scores He Dreiht work

Heerema scores He Dreiht work

Photo source: Heerema

Heerema Marine Contractors has been contracted by EnBW to transport and install monopiles and transition pieces at the He Dreiht offshore wind farm. 

The work includes the transport and installation of 64 monopiles and transition pieces. During operations, Heerema will use the IHC IQIP double-walled noise mitigation system NMS-10,000 amongst other systems to reduce noise pollution.

Heerema CEO, Koos-Jan van Brouwershaven said, “We are delighted to be EnBW’s chosen contractor, and we must credit the Heerema team and our client for their excellent collaboration in finding the most suited solutions for the He Dreiht project.”

He Dreiht Wind Farm

The He Dreiht wind farm is located in the German North Sea, 90 km northwest of Borkum and about 110 km west of Heligoland. With a capacity of 900 MW, He Dreiht is one of the largest planned offshore wind power projects in Europe and is scheduled to go into operation in 2025.

Heerema’s offshore wind director, Jeroen van Oosten said, “We are committed to increasing our market share in large monopile installations for offshore wind, and are proud to be chosen to enable EnBW to deliver 900 MW of renewable energy.”

EnBW He Dreiht project director, Jörn Däinghaus added, “Heerema is a contractor with a high level of experience and excellent technological know-how. We look forward to working with Heerema to develop and install our first subsidy-free offshore windpark.”

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.