Van Oord brings everyone onboard a TP installation
Video

Van Oord brings everyone onboard the Baltic Eagle TP installation

Photo: Van Oord

After Van Oord’s heavy lift installation vessel, Svanen completed the installation of all fifty monopiles for Iberdrola Deutschland’s Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation.

To complete the foundations for the wind turbines, the company is currently installing the transition pieces on the previously installed monopiles. The transition pieces were transported from the manufacturing yard in Aviles to the Van Oord storage facility in Mukran, Germany. At Van Oord’s facility, the final preparations and equipment is installed to enable the installation.

Van Oord has just brought in Jumbo Offshore to transport and install transition pieces for the Baltic Eagle offshore wind project. In addition, the company has brought everyone on board the TP installation process through a short vlog with Ingmar Kuipers, Offshore Construction Manager.

The next step of the construction is the inter-array cable installation. Loading onto Van Oord’s cable-laying vessel Nexus has commenced already.

In total, Van Oord will install approximately 70 kilometres of 66kV inter-array cables, manufactured by subcontractor TKF. To protect the cables, Van Oord will deploy its trencher Dig-It later this year to bury them. This Tracked Remotely Operated Vehicle (TROV) drives unmanned over the seabed and creates a trench for the cables by liquefying the seabed.

Luis Pérez Portela, Baltic Eagle Director at Iberdrola, ‘Very key milestones are being completed in the construction site and we’re looking forward to completing all installation work before commissioning can begin. I’d like to thank all vendors, suppliers, partners and staff for their commitment and perseverance which is allowing us to deliver this important project.’

Henk Jan van Dijk, Project Director at Van Oord,  ‘The installation of the monopiles marks a key milestone in the construction of the Baltic Eagle offshore wind farm. The contours are now visible. Now that the transition pieces are being installed and our cable-laying vessel is ready to install the inter-array cables, construction is progressing well. A big thanks to the dedicated project team and all our partners driving this project.’

The Baltic Eagle offshore wind farm is located 30 kilometres northeast of the German island of Rügen and covers a 40 square kilometre area. With a production capacity of 476 MW, Iberdrola’s Baltic Eagle offshore wind farm will deliver renewable energy to 475,000 households while reducing carbon dioxide emissions by approximately 800,000 tonnes annually. It is scheduled to be fully operational by the end of 2024. Van Oord is responsible for the transport and installation of the wind turbine foundations and the supply, transport and installation of the inter-array cables.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Van Oord brings everyone onboard the Baltic Eagle TP installation | Project Cargo Journal
Van Oord brings everyone onboard a TP installation
Video

Van Oord brings everyone onboard the Baltic Eagle TP installation

Photo: Van Oord

After Van Oord’s heavy lift installation vessel, Svanen completed the installation of all fifty monopiles for Iberdrola Deutschland’s Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation.

To complete the foundations for the wind turbines, the company is currently installing the transition pieces on the previously installed monopiles. The transition pieces were transported from the manufacturing yard in Aviles to the Van Oord storage facility in Mukran, Germany. At Van Oord’s facility, the final preparations and equipment is installed to enable the installation.

Van Oord has just brought in Jumbo Offshore to transport and install transition pieces for the Baltic Eagle offshore wind project. In addition, the company has brought everyone on board the TP installation process through a short vlog with Ingmar Kuipers, Offshore Construction Manager.

The next step of the construction is the inter-array cable installation. Loading onto Van Oord’s cable-laying vessel Nexus has commenced already.

In total, Van Oord will install approximately 70 kilometres of 66kV inter-array cables, manufactured by subcontractor TKF. To protect the cables, Van Oord will deploy its trencher Dig-It later this year to bury them. This Tracked Remotely Operated Vehicle (TROV) drives unmanned over the seabed and creates a trench for the cables by liquefying the seabed.

Luis Pérez Portela, Baltic Eagle Director at Iberdrola, ‘Very key milestones are being completed in the construction site and we’re looking forward to completing all installation work before commissioning can begin. I’d like to thank all vendors, suppliers, partners and staff for their commitment and perseverance which is allowing us to deliver this important project.’

Henk Jan van Dijk, Project Director at Van Oord,  ‘The installation of the monopiles marks a key milestone in the construction of the Baltic Eagle offshore wind farm. The contours are now visible. Now that the transition pieces are being installed and our cable-laying vessel is ready to install the inter-array cables, construction is progressing well. A big thanks to the dedicated project team and all our partners driving this project.’

The Baltic Eagle offshore wind farm is located 30 kilometres northeast of the German island of Rügen and covers a 40 square kilometre area. With a production capacity of 476 MW, Iberdrola’s Baltic Eagle offshore wind farm will deliver renewable energy to 475,000 households while reducing carbon dioxide emissions by approximately 800,000 tonnes annually. It is scheduled to be fully operational by the end of 2024. Van Oord is responsible for the transport and installation of the wind turbine foundations and the supply, transport and installation of the inter-array cables.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.