Jumbo Offshore has officially closed its scope of work for the Baltic Eagle offshore wind farm in the German Baltic Sea. The scope of work included the installation of 50 transition pieces in partnership with...Read more
Foundation and inter-array cables installation for Iberdrola’s Baltic Eagle offshore wind farm in the German Baltic Sea, 30 kilometres northeast of the island of Rügen is completed. Van Oord wrapped up the job as it...Read more
Within months after vessel reservation, and weeks after unveiling the contract with Van Oord, Jumbo Offshore has installed the first 20 transition pieces for the Baltic Eagle project. Read more
VideoAfter Van Oord’s heavy lift installation vessel, Svanen completed the installation of all fifty monopiles for Iberdrola Deutschland’s Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation.Read more
Jumbo Offshore, a Jumbo Maritime company, has continued its cooperation with Van Oord. Following cooperation on the Arkona offshore wind farm, the company has now again been awarded a contract to transport and install transition...Read more
Various offshore wind projects have recently brought together three vessels that are part of the Spliethoff Group to the Port of Aviles in Spain.Read more
The first monopile out of 50 to be installed at the Baltic Eagle offshore wind farm is sitting in place, as Van Oord’s heavy-lift vessel Svanen completed the installation. Read more
The first transition pieces manufactured by Windar Renovables at its facilities in Avilés for the Baltic Eagle wind farm have been delivered. The vessel, BigLift Shipping’s Happy Dragon, has loaded the transition pieces and has...Read more
Earlier this month, Heerema Marine Contractors’ semi-submersible crane vessel Thialf installed the 4,200 – metric tonne topside of the Baltic Eagle offshore wind farm, for Iberdrola Renewables.Read more
deugro, in collaboration with dteq Transport Engineering Solutions (dteq), delivered eight pin piles from Bilbao, Spain to Vlissingen, Netherlands as part of the Baltic Eagle offshore wind farm project. The 77-meter-long pin piles, with a...Read more
Heerema Marine Contractors have been tagged by Baltic Eagle to transport and install the offshore substation (OSS) for the Baltic Eagle offshore wind farm. Read more
Van Oord has signed a contract with the Spanish energy company Iberdrola for the Baltic Eagle offshore wind farm. Van Oord will transport and install the foundations and ensure the supply, transport and installation of...Read more