![Jumbo Offshore wraps up its scope of Baltic Eagle work](https://www.projectcargojournal.com/wp-content/uploads/2023/12/Jumbo-Offshore-wraps-up-its-scope-of-Baltic-Eagle-work-128x128.jpeg)
![Jumbo Offshore wraps up its scope of Baltic Eagle work](https://www.projectcargojournal.com/wp-content/uploads/2023/12/Jumbo-Offshore-wraps-up-its-scope-of-Baltic-Eagle-work-128x128.jpeg)
![Baltic Eagle offshore wind farm foundation installation done](https://www.projectcargojournal.com/wp-content/uploads/2023/12/Baltic-Eagle-offshore-wind-farm-foundation-installation-done-128x128.jpg)
Baltic Eagle offshore wind farm foundation installation done
Foundation and inter-array cables installation for Iberdrola’s Baltic Eagle offshore wind farm in the German Baltic Sea, 30 kilometres northeast of the island of Rügen is completed. Van Oord wrapped up the job as it...Read more![Jumbo Offshore installs the first 20 Baltic Eagle TPs](https://www.projectcargojournal.com/wp-content/uploads/2023/11/Jumbo-Offshore-installs-the-first-20-Baltic-Eagle-TPs-128x128.jpeg)
Jumbo Offshore installs the first 20 Baltic Eagle TPs
Within months after vessel reservation, and weeks after unveiling the contract with Van Oord, Jumbo Offshore has installed the first 20 transition pieces for the Baltic Eagle project. Read more![Van Oord brings everyone onboard a TP installation](https://www.projectcargojournal.com/wp-content/uploads/2023/10/Van-Oord-brings-everyone-onboard-a-TP-installation-128x128.jpeg)
Van Oord brings everyone onboard the Baltic Eagle TP installation
VideoAfter Van Oord’s heavy lift installation vessel, Svanen completed the installation of all fifty monopiles for Iberdrola Deutschland’s Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation.Read more![Jumbo and Van Oord cooperation continues as Baltic Eagle deal is agreed](https://www.projectcargojournal.com/wp-content/uploads/2023/10/Jumbo-and-Van-Oord-cooperation-continues-as-Baltic-Eagle-deal-is-agreed-128x128.jpeg)
Jumbo and Van Oord cooperation continues as Baltic Eagle deal is agreed
Jumbo Offshore, a Jumbo Maritime company, has continued its cooperation with Van Oord. Following cooperation on the Arkona offshore wind farm, the company has now again been awarded a contract to transport and install transition...Read more![Baltic Eagle project cargo brings a heavy lift trio to Aviles](https://www.projectcargojournal.com/wp-content/uploads/2023/05/Baltic-Eagle-project-cargo-brings-a-heavy-lift-trio-to-Aviles-128x128.png)
Offshore wind components bring a heavy lift trio to Aviles
Various offshore wind projects have recently brought together three vessels that are part of the Spliethoff Group to the Port of Aviles in Spain.Read more![Heavy-lift vessel Svanen installs first of 50 Baltic Eagle monopiles](https://www.projectcargojournal.com/wp-content/uploads/2023/04/Heavy-lift-vessel-Svanen-installs-first-of-50-Baltic-Eagle-monopiles-128x128.jpg)
Heavy-lift vessel Svanen installs first of 50 Baltic Eagle monopiles
The first monopile out of 50 to be installed at the Baltic Eagle offshore wind farm is sitting in place, as Van Oord’s heavy-lift vessel Svanen completed the installation. Read more![First Baltic Eagle wind farm transition pieces delivered](https://www.projectcargojournal.com/wp-content/uploads/2023/03/First-Baltic-Eagle-wind-farm-transition-pieces-delivered-128x128.jpeg)
First Baltic Eagle wind farm transition pieces delivered
The first transition pieces manufactured by Windar Renovables at its facilities in Avilés for the Baltic Eagle wind farm have been delivered. The vessel, BigLift Shipping’s Happy Dragon, has loaded the transition pieces and has...Read more![Baltic Eagle’s offshore substation now in place](https://www.projectcargojournal.com/wp-content/uploads/2023/02/Thialf-en-route-Brae-Bravo-4-Low-Res-128x128.jpeg)
Heerema installs Baltic Eagle OWF substation
Earlier this month, Heerema Marine Contractors’ semi-submersible crane vessel Thialf installed the 4,200 – metric tonne topside of the Baltic Eagle offshore wind farm, for Iberdrola Renewables.Read more![deugro teams up with dteq for Baltic Eagle pin piles delivery to Vlissingen](https://www.projectcargojournal.com/wp-content/uploads/2022/09/deugro-teams-up-with-dteq-for-Baltic-Eagle-pin-piles-delivery-to-Vlissingen-128x128.jpeg)
deugro teams up with dteq for Baltic Eagle pin piles delivery to Vlissingen
deugro, in collaboration with dteq Transport Engineering Solutions (dteq), delivered eight pin piles from Bilbao, Spain to Vlissingen, Netherlands as part of the Baltic Eagle offshore wind farm project. The 77-meter-long pin piles, with a...Read more![Heerema grabs Baltic Eagle OSS transport and installation job](https://www.projectcargojournal.com/wp-content/uploads/2022/03/Heerma-grabs-Baltics-Eagle-OSS-transport-and-installation-job-128x128.jpeg)
Heerema grabs Baltic Eagle OSS transport and installation job
Heerema Marine Contractors have been tagged by Baltic Eagle to transport and install the offshore substation (OSS) for the Baltic Eagle offshore wind farm. Read more![Van Oord bags Baltic Eagle OWF job from Iberdrola](https://www.projectcargojournal.com/wp-content/uploads/2021/07/Van-Oord-bags-Baltic-Eagle-OWF-job-from-Iberdrola-128x128.jpg)