Chemical Park Leuna gets two new reactors

Chemical Park Leuna gets two new reactors

Photo:DAKo Worldwide Transport

German freight forwarding and heavy transport exports, DAKO Worldwide Transport and Bohnet, recently joined forces to move reactors from Hamburg to Leuna. Both units were delivered to the Chemical Park Leuna. 

DAKO Worldwide Transport received the two units weighing 142.5 tons each from under hook in Hamburg, following their delivery from China. From Hamburg, the company deployed a barge to ship the two reactors via the river Elbe to the port of Aken. There, both units were transloaded onto hydraulic trailers.

Chemical Park Leuna gets two new reactors
Each reactor weighed 142.5 tons

In partnership with Bohnet, DAKO then transported the transformers from Aken some 90 kilometres to Leuna. The transport was executed within over two nights.

The transport was not straightforward as space constrictions and height obstacles at the job site presented a challenge. The two units had to be re-loaded onto a configuration with a lowbed to allow for manoeuvring and transport up to the final place of erection.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Chemical Park Leuna gets two new reactors | Project Cargo Journal
Chemical Park Leuna gets two new reactors

Chemical Park Leuna gets two new reactors

Photo: DAKo Worldwide Transport

German freight forwarding and heavy transport exports, DAKO Worldwide Transport and Bohnet, recently joined forces to move reactors from Hamburg to Leuna. Both units were delivered to the Chemical Park Leuna. 

DAKO Worldwide Transport received the two units weighing 142.5 tons each from under hook in Hamburg, following their delivery from China. From Hamburg, the company deployed a barge to ship the two reactors via the river Elbe to the port of Aken. There, both units were transloaded onto hydraulic trailers.

Chemical Park Leuna gets two new reactors
Each reactor weighed 142.5 tons

In partnership with Bohnet, DAKO then transported the transformers from Aken some 90 kilometres to Leuna. The transport was executed within over two nights.

The transport was not straightforward as space constrictions and height obstacles at the job site presented a challenge. The two units had to be re-loaded onto a configuration with a lowbed to allow for manoeuvring and transport up to the final place of erection.