The Dutch subsea cable specialist WIND has secured a contract to provide cable transfers and cable storage for offshore spare export cables for TenneT. Read more
Boskalis heavy transport vessel Mighty Servant 3 has completed the transport of Tennet’s Beta substation of the Hollandse Kust Zuid wind farm. Boskalis noted that the involvement in such projects is its way of taking...Read more
The 700 MW Hollandse Kust Zuid (HKZ) Beta topside weighing 3,950-tonnes has been loaded out at the Drydocks World Dubai and is on its way to the Netherlands. Petrofac informed that it has completed the...Read more
The 700 MW Alpha topside for the Hollandse Kust Zuid (HKZ) project has been completed by Drydocks World (DDW). The unit has already sailed away from the fabrication yard in Dubai to the Netherlands onboard...Read more
The jacket foundation for TenneT’s Hollandse Kust (noord) substation has been installed in a joint operation by DEME Offshore and Scaldis SMC. The 2,100-tonne jacked installation has been completed by the heavy lift vessel Gulliver. Read more
Heerema Marine Contractors’ LNG-fueled semi-submersible crane vessel Sleipnir has completed the installation of the second jacket of TenneT’s offshore transformer platforms for the Hollandse Kust Zuid (HKZ) wind farm in the North Sea.Read more
Denmark has approved a plan to build the first energy hub in the North Sea. This is a small artificial island where the connections of wind farms converge. The energy can then be transported to...Read more
Offshore windHeerema Fabrication Group will construct the Hollandse Kust (noord) offshore transformer substation jacket. The contract for this was signed with Iemants (part of Smulders). The jacket will be 44 metres high and consists of 1600...Read more
Offshore windThe first jacket of TenneT’s Hollandse Kust (Zuid) offshore platform has been installed in the seabed. The heavyweight Alpha jacket of 3200 tonnes was transported and installed by Heerema’s heavy lift crane vessel Sleipnir.Read more
Offshore windPRESS RELEASE – Blue Offshore has moved 8,000 tonnes of high voltage cable to Rotterdam. The cables will form the connection of Tennet’s Hollandse Kust Zuid Alpha Platform to the onshore grid.Read more