Allelys gets 199-tonne Keith substation project cargo on the move

Allelys gets 199-tonne Keith substation project cargo on the move

Photo source: Allelys

UK’s transport and heavy lift specialist Allelys have recently completed the delivery of two 199-tonne rotors and two 62-tonne stators for Keith Substation in Scotland. The company has taken the units on a 120-mile journey from Rugby to Goole Port, and further on from Buckie Port to the construction site. 

The components were delivered in two phases, two months apart with one rotor and one stator being transported and installed during each phase. The 62-tonne stators were transported using neck 7 modular trailers, whereas Allelys 200-tonne girder frame was utilised to transport the 199-tonne rotors.

Due to the route survey identifying a weak bridge along the route, Allelys organised a motorway closure to transport the rotors contraflow to avoid the bridge.

Allellys moving project cargo for Keith substation
Photo source: Allelys

Once the transport arrived at Goole Port, Allelys’ joint venture company provided a 1,000-tonne mobile crane to lift the units onto the vessel for onward marine transport to Buckie Port.

After completing the 425 mile journey to Buckie Port, the components were lifted off the vessel using a 1,000-tonne crane back onto the original transport arrangements and transported to site.

Read also: Allelys wraps up transport for a UK power project

The final scope of work for Allelys was to complete the installation. Due to the dimensions of the unit and the position of the plinth, the engineering team designed lifting beams specifically for this project. The rotor was lifted from the transport onto a specially constructed frame to allow the stator to be rotated and inserted over the shaft of the rotor into its final position.

“This was a great project to work on and one that saw Allelys not only offering transport solutions, but also supporting the project with route surveys, bespoke fabrications, engineering and project management too,” explains Craig Mackay, operations manager – projects at Allelys.

Allellys moving project cargo for Keith substation
Photo source: Allelys

Read also: Allelys shunts 184-ton transformer from Ipswich to Burwell

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

Allelys gets 199-tonne Keith substation project cargo on the move | Project Cargo Journal
Allelys gets 199-tonne Keith substation project cargo on the move

Allelys gets 199-tonne Keith substation project cargo on the move

Photo source: Allelys

UK’s transport and heavy lift specialist Allelys have recently completed the delivery of two 199-tonne rotors and two 62-tonne stators for Keith Substation in Scotland. The company has taken the units on a 120-mile journey from Rugby to Goole Port, and further on from Buckie Port to the construction site. 

The components were delivered in two phases, two months apart with one rotor and one stator being transported and installed during each phase. The 62-tonne stators were transported using neck 7 modular trailers, whereas Allelys 200-tonne girder frame was utilised to transport the 199-tonne rotors.

Due to the route survey identifying a weak bridge along the route, Allelys organised a motorway closure to transport the rotors contraflow to avoid the bridge.

Allellys moving project cargo for Keith substation
Photo source: Allelys

Once the transport arrived at Goole Port, Allelys’ joint venture company provided a 1,000-tonne mobile crane to lift the units onto the vessel for onward marine transport to Buckie Port.

After completing the 425 mile journey to Buckie Port, the components were lifted off the vessel using a 1,000-tonne crane back onto the original transport arrangements and transported to site.

Read also: Allelys wraps up transport for a UK power project

The final scope of work for Allelys was to complete the installation. Due to the dimensions of the unit and the position of the plinth, the engineering team designed lifting beams specifically for this project. The rotor was lifted from the transport onto a specially constructed frame to allow the stator to be rotated and inserted over the shaft of the rotor into its final position.

“This was a great project to work on and one that saw Allelys not only offering transport solutions, but also supporting the project with route surveys, bespoke fabrications, engineering and project management too,” explains Craig Mackay, operations manager – projects at Allelys.

Allellys moving project cargo for Keith substation
Photo source: Allelys

Read also: Allelys shunts 184-ton transformer from Ipswich to Burwell

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.